Bill Details

HR.1722 - 119th Congress

Track Billion Dollar Boondoggle Act of 2025? Stop tracking Billion Dollar Boondoggle Act of 2025?

When you track this bill you will receive emails when the bill has been updated.

You will no longer receive emails when this bill is updated.

Status
  1. Introduced
  2. Passed House
  3. Passed Senate
  4. To President
  5. Law
Latest action
2026-03-18 - Ordered to be Reported (Amended) by the Yeas and Nays: 39 - 0.
Introduced Date
2025-02-27
Policy Area
Government Operations and Politics
6
0

AI Summary This summary was generated by AI from the bill text. AI can get information wrong.

This bill would require the federal government to make a yearly public report on expensive taxpayer-funded projects that are badly delayed or way over budget. It directs the Office of Management and Budget to set up the reporting rules within one year, and then agencies would have to send in information about these troubled projects every year. The report must be sent to Congress and posted online so the public can see which projects are falling behind, how much they are costing, and why the problems happened.

  • It applies to executive agencies and independent regulatory agencies.
  • A project is covered if it is more than 5 years behind schedule, or if costs have gone at least $1 billion above the original estimate.
  • Covered projects include major purchases, defense programs, construction, cleanup efforts, and other time-limited federal projects.
  • Agencies must report details like the project’s purpose, location, start date, contractors, changes in scope, original and current completion dates, original and current costs, reasons for delays or cost increases, and any bonuses or incentive fees paid.

Official Summaries

Billion Dollar Boondoggle Act of 2025

This bill requires the Office of Management and Budget (OMB) to collect information from federal agencies and report to Congress regarding projects that are behind schedule or have expenditures that have exceeded the original cost estimate. 

Specifically, the bill requires OMB to issue guidance directing federal agencies to annually submit specified information to OMB regarding certain federally funded projects that (1) are more than five years behind schedule, or (2) have expenditures that are at least $1 billion more than the original cost estimate for the project. 

Among other information, the agencies must submit to OMB

  • a description of each project;
  • an explanation of any change to the original scope of the project;
  • the original and current expected dates for the completion of the project;
  • the original and current cost estimates adjusted for inflation; 
  • an explanation for any delays in completing the project or increases in the cost; and
  • the amount of and rationale for any award, incentive fee, or other type of bonus awarded for the project.

The bill also requires OMB to submit an annual report to Congress containing the information submitted by the agencies and post the report on the OMB website. 

Current Full Text

[Congressional Bills 119th Congress]
[From the U.S. Government Publishing Office]
[H.R. 1722 Introduced in House (IH)]

<DOC>






119th CONGRESS
  1st Session
                                H. R. 1722

 To require an annual report of taxpayer-funded projects that are over 
                      budget and behind schedule.


_______________________________________________________________________


                    IN THE HOUSE OF REPRESENTATIVES

                           February 27, 2025

Mrs. Miller-Meeks introduced the following bill; which was referred to 
 the Committee on Oversight and Government Reform, and in addition to 
   the Committee on Armed Services, for a period to be subsequently 
   determined by the Speaker, in each case for consideration of such 
 provisions as fall within the jurisdiction of the committee concerned

_______________________________________________________________________

                                 A BILL


 
 To require an annual report of taxpayer-funded projects that are over 
                      budget and behind schedule.

    Be it enacted by the Senate and House of Representatives of the 
United States of America in Congress assembled,

SECTION 1. SHORT TITLE.

    This Act may be cited as the ``Billion Dollar Boondoggle Act of 
2025''.

SEC. 2. ANNUAL REPORT.

    (a) Definitions.--In this section--
            (1) the term ``covered agency'' means--
                    (A) an Executive agency, as defined in section 105 
                of title 5, United States Code; and
                    (B) an independent regulatory agency, as defined in 
                section 3502 of title 44, United States Code;
            (2) the term ``covered project'' means a project funded by 
        a covered agency--
                    (A) that is more than 5 years behind schedule, as 
                measured against the original expected date for 
                completion; or
                    (B) for which the amount spent on the project is 
                not less than $1,000,000,000 more than the original 
                cost estimate for the project;
            (3) the term ``Director'' means the Director of the Office 
        of Management and Budget; and
            (4) the term ``project'' means a major acquisition, a major 
        defense acquisition program (as defined in section 4201 of 
        title 10, United States Code), a procurement, a construction 
        project, a remediation or clean-up effort, or any other time-
        limited endeavor, that is not funded through direct spending 
        (as defined in section 250(c) of the Balanced Budget and 
        Emergency Deficit Control Act of 1985 (2 U.S.C. 900(c))).
    (b) Requirements.--
            (1) Submission.--Not later than 1 year after the date of 
        enactment of this Act, the Director shall issue guidance 
        requiring covered agencies to, on an annual basis, submit to 
        the Director information relating to each covered project of 
        the covered agency, which shall include--
                    (A) a brief description of the covered project, 
                including--
                            (i) the purpose of the covered project;
                            (ii) each location in which the covered 
                        project is carried out;
                            (iii) the contract or award number of the 
                        covered project, where applicable;
                            (iv) the year in which the covered project 
                        was initiated;
                            (v) the Federal share of the total cost of 
                        the covered project; and
                            (vi) each primary contractor, 
                        subcontractor, grant recipient, and subgrantee 
                        recipient of the covered project;
                    (B) an explanation of any change to the original 
                scope of the covered project, including by the addition 
                or narrowing of the initial requirements of the covered 
                project;
                    (C) the original expected date for completion of 
                the covered project;
                    (D) the current expected date for completion of the 
                covered project;
                    (E) the original cost estimate for the covered 
                project, as adjusted to reflect increases in the 
                Consumer Price Index for All Urban Consumers, as 
                published by the Bureau of Labor Statistics;
                    (F) the current cost estimate for the covered 
                project, as adjusted to reflect increases in the 
                Consumer Price Index for All Urban Consumers, as 
                published by the Bureau of Labor Statistics;
                    (G) an explanation for a delay in completion or an 
                increase in the original cost estimate for the covered 
                project, including, where applicable, any impact of 
                insufficient or delayed appropriations; and
                    (H) the amount of and rationale for any award, 
                incentive fee, or other type of bonus, if any, awarded 
                for the covered project.
            (2) Report.--The Director shall submit to Congress and post 
        on the website of the Office of Management and Budget an annual 
        report containing the information submitted under paragraph (1) 
        for the relevant year.
                                 <all>